The need to increase the rail gauge clearance to accommodate increased W10 size freight wagons recently led to the replacement of the traditional brick arch structure at Gipsy Lane in Nuneaton.
With rail closures only possible for weekend possessions, a fully pre-cast concrete solution was chosen. The ‘kit’ bridge comprised 8 cill beam elements, 13 TY internal and 2 TYE edge beams each with stringcourse and parapet units cast on. The whole structure was pre-erected (see photo) to ensure that the replacement could be erected over a single weekend.
Contractor, VolkerFitzpatrick successfully completed the demolition and replacement of the bridge over two consecutive weekends in October, 2009.
Photo: Pre-delivery trial erection at ABM’s Tuxford Plant
Photo: Detail of the decorative parapet wall feature
The need to increase the rail gauge clearance to accommodate increased W10 size freight wagons recently led to the replacement of the traditional brick arch structure at Gipsy Lane in Nuneaton.
continueABM Precast Solutions have completed supply of three pre-stressed beam bridge structures (two river and one rail) to Birse Civils for the B1115 Stowmarket Relief Road.
continueYears of heavy traffic around Shenstone Station in Staffordshire has taken its toll on the adjacent bridge approach embankments and led to an innovative stabilisation project.