A46 Newark to Widmerpool Improvements

Project A46 Newark to Widmerpool Improvements
Client Highways Agency
Stage Complete
Location A46 Newark to Widmerpool Improvements, Nottinghamshire

Products Supplied

Description Quantity Weight
17.9m long Y6 Beams 18 21.6 tonnes (each unit)
22.83m long Y8 Beams 18 32.7 tonnes (each unit)
22.66m long Y8 Beams 18 33.8 tonnes (each unit)
15.897m long TY8 Beams 33 11.3 tonnes (each unit)

Project Details

As part of a £220 million Highways Agency ECI contract, Balfour Beatty and design partner Scott Wilson (URS) chose to take full advantage of the benefits of precast concrete construction in all of the underbridges on the 28km improvement of the A46 between Newark and Widmerpool. 87 prestressed bridge beams in total measuring nearly 1.7km form the heart of the four underbridge structures including the busy A46/A52 Saxondale interchange.

 
Key Personnel

Main Board Directors
Pat O'Neill
Sean Minihane
Brendan O'Neill

Sustainability

ABM Europe is wholly committed to the concept of sustainability throughout all aspects of the business through the implementation of environmental...

Our Mission & Vision

ABM’s mission is to deliver exceptional quality structures, buildings and products on a continual basis that exceed our clients’ expectations...