Bridge Over Kaszow City, Road No. DW780, km 1,346

Project Bridge over the Kaszów city, road number DW780, km 1 346
Client Zarzad Drog Wojewodzkich w Krakowie
Stage Complete
Description ABM prefabricated the reinforced concrete rectangular section for the upper element

Fact File

Structure ABM prefabricated the reinforced concrete rectangular section for the upper element
Span 8.0m
Height 2.91m
Length 10m (4 segments of 2.5m)

Requirements

Installation of the superstructure took only 1 day. The rapid assembly coupled with the manufacture of the prefabricated elements off-site, ABM minimised traffic congestion and adverse impact on the environment within the structure.

An additional advantage of such rapid assembly is the minimisation of risks associated with the works carried out on site..

Despite the short installation period of the supporting structure, it retains its durability and lifespan. This, in turn equates to minimal maintenance costs for the facility manager.

Costs relating to the construction of prefabricated reinforced concrete are very competitive against choices of other technologies.

Click here to view a YouTube video of the construction of the Renault F1 facility

 
Key Personnel

Main Board Directors
Pat O'Neill
Sean Minihane
Brendan O'Neill

Sustainability

ABM Europe is wholly committed to the concept of sustainability throughout all aspects of the business through the implementation of environmental...

Our Mission & Vision

ABM’s mission is to deliver exceptional quality structures, buildings and products on a continual basis that exceed our clients’ expectations...