Highway R3 - Horna Stubna Bypass, SO 201

Project Highway R3 - Horna Stubna Bypass, SO 201
Client NDS a.s. (Slovak Highway Agency)
Stage Complete
Description Construction of the new railway bridge over the newly constructed highway

Fact File

Structure OC 13.5m x 7,0m frame precast system
Span 13.5m (internal)
Height 7.0m (internal)
Length 33.7m (19 rings of 1,75m)

Requirements

  • Fastest solution for the construction of the new bridge
  • Allow for the option to extend the bridge, to accommodate a future extension of the highway to 2+2 lanes
  • Minimizing the risks associated with a built-in-situ structure
  • A fast solution with minimum impact to the building site traffic and the environment
  • An alternative to massive built-in-situ abutments and the related construction processes and technologies
  • Use of a frame precast system on slab raft foundation
  • Using 8m high wing-walls
  • Overall construction of the bridge and thus total rail possession in only 43 days
  • Eliminated the requirement for a temporary bridge
  • The main route was not blocked for the site traffic during installation

Click here to view a YouTube video of how ABM construct a bridge in 3 days

 
Key Personnel

Main Board Directors
Pat O'Neill
Sean Minihane
Brendan O'Neill

Sustainability

ABM Europe is wholly committed to the concept of sustainability throughout all aspects of the business through the implementation of environmental...

Our Mission & Vision

ABM’s mission is to deliver exceptional quality structures, buildings and products on a continual basis that exceed our clients’ expectations...