Description Demolition of existing maintenance facility and decontamination and removal of existing below ground diesel tanks and construction of new facility.

Project Details

This project consisted of the demolition of the existing maintenance facility and decontamination and removal of existing below-ground diesel tanks.

The new facility consisted of 800sqm portal frame with 150sqm of first floor offices. Externally a new 10,000 litre below ground petrol and diesel tank was installed. for the duration of the project the existing irrigation system within the existing structure was kept live and the new facility was constructed around the pump house.

 

 
Key Personnel

Main Board Directors
Pat O'Neill
Sean Minihane
Brendan O'Neill

Sustainability

ABM Europe is wholly committed to the concept of sustainability throughout all aspects of the business through the implementation of environmental...

Our Mission & Vision

ABM’s mission is to deliver exceptional quality structures, buildings and products on a continual basis that exceed our clients’ expectations...